Walka Water Works to partially reopen in November with remediation works to start
After detailed assessments across the Walka Water Works site, a remediation plan has been developed and Maitland City Council has worked with Crown Lands to expedite reopening parts of the site to the community under interim controls.
Work starting in the coming weeks will restore access to Walka via both Scobies Lane and Pumphouse Road, reopen the walking and running trails to the public, and reopening the car park and toilet block.
Upcoming works include the installation of fencing, signage, and capping of specific areas to restrict hazardous areas and allow recreational use of the site. Asbestos air monitoring will also be in place to ensure no ongoing risk to the public.
Mayor Philip Penfold hailed the partial reopening as great news.
'We know the closure of Walka Water Works came as a shock and we’re really pleased to be moving towards a safe, partial reopening of the site,' Mayor Penfold said.
'Council has worked very closely with Crown Lands on this journey and I’d like to thank them for their determination and willingness to come to the table and help us bring this facility back to the community.
'There are many in the community that will benefit from this partial reopening, like Maitland Parkrun and all the walkers, riders, and runners that regularly make use of Walka Water Works.
'We thank everyone for their patience while we continue to work through the issues at the site, and we're all looking forward to getting back out there and enjoying one of Maitland’s most loved facilities.'
General Manager, David Evans said the community should expect conditions will continue to change at Walka as remediation works continue.
‘With the risk of asbestos contamination still present at Walka, our ground maintenance crews won’t be able to maintain the previous levels of presentation,’ Mr Evans said.
‘Once we’re able to get back in there safely, we’ll restore those high standards as soon as possible.
‘There is also likely to be the need to close the site periodically while remediation works are ongoing, to allow that work to happen and for public safety, but we’ll strive to ensure any disruptions to the community are minimised.’
Details of a broader remediation plan will be released in the coming months, with Council officers working towards addressing issues across the whole site in partnership with Crown Lands.
Council will keep the community informed as to the progress of the works and we look forward to announcing a firm partial reopening date soon.
News details
- My Neighbourhood
- My Council
- About Council
- Council meetings
- Guiding Principles
- Public Notice of Development Consents
- Councillors
- How does Council work?
- Our organisation
- Committees
- Ward boundaries
- Freedom of Entry
- Civic Traditions
- Demystifying Council
- Councillors Information
- Draft Code of Meeting Practice
- Draft Councillor Expenses and Facilities Policy
- Public exhibition and notices
- Governance and transparency
- News and updates
- Work with us
- Planning and reporting
- Long term planning
- Maitland +10 Community Strategic Plan
- Delivery Program
- Operational Plan
- Fees and Charges
- General Purpose Financial Reports
- Resourcing Strategy
- Asset Management Plan
- Maitland Urban Settlement Strategy
- Local Environment Plan (LEP)
- Development Control Plan (DCP)
- Maitland Local Strategic Planning Statement 2040+
- Community Satisfaction Results
- Destination Management Plan
- Annual report
- Publications, plans and strategies
- Central Maitland Interpretation Plan
- Aberglassyn Structure Plan
- Manual of Engineering Standards
- Activity Centres and Employment Clusters Strategy
- Central Maitland Structure Plan
- Gilleston Heights Structure Plan
- Hunter River Branxton to Green Rocks flood study (2010)
- Hunter River Floodplain Risk Management Study and Plan (2015)
- Lochinvar Structure Plan
- Maitland Centres Study (2009)
- Maitland Integrated Land Use and Transport Study
- Maitland Rural Lands Strategy (2005)
- Thornton Structure Plan
- Maitland Bike Plan
- Discussion paper: Strengthening relationships with young people
- Rutherford Youth Protocol
- Disability Inclusion Action Plan (DIAP)
- Community Facilities and Services Strategy
- Lochinvar Flood Study
- Maitland Recreation and Open Space Strategy
- Open Museums Open Minds
- Wallis and Swamp-Fishery Creek Flood Study
- Long term planning
- Works and major projects
- Maitland Your Say
- About Council
- Our Services
- Waste and recycling
- Building and development
- Planning Portal
- Planning information and advice
- Building and renovating
- The application process
- Planning strategies
- Property certificates
- Online Mapping
- Development contributions
- Planning application forms and certificates
- Short Term Licence to Access Council Owned or Managed Land
- Register of variations
- Community
- Community Notices
- Community services
- Citizenship ceremonies
- Grants and Sponsorship
- Education programs
- Environmental education
- Living sustainably
- Library education programs
- Art Gallery creative learning programs
- Maitland Gaol education programs
- Heritage education programs
- Service awards
- Australian Death Notification Service
- Cemeteries
- Environment
- Council’s environmental actions and commitments
- Snakes in Maitland
- Estuary management
- Maitland Greening Plan
- Native Seedling Giveaway
- Community Street Tree Planting Program
- Weeds and pesticides
- Environmental Education
- Living sustainably
- Green Communities Newsletter
- Interested in Landcare near you?
- Solar power and your home
- Your Bushland Reserves
- Roads, traffic and transport
- Business and economy
- Economic statistics and investment
- Your business
- Economic Strategy
- Permits and approvals
- Submitting a tender to Council
- Visitor Economy
- Play & Explore
- Events
- Facilities and recreation
- Arts and culture
- History and heritage
- Resident guide
- Visiting Maitland