Haussman Drive Upgrade

Project Status

Complete
Stage 1 - Concept design
Completed 2016/17
Complete
Stages 2 and 3 - Concept design
Completed 2017/18
Complete
Stage 1 - Community engagement
October 2018
Complete
Stage 1 - Detail design
Completed October 2019
Complete
Stage 1 - Construction
Completed February 2021
Complete
Stage 2 - Detailed design
Commenced 2021
Current
Stage 2A
Early works
Upcoming
Stage 2A - Construction of Taylor Avenue roundabout and duplication of Haussman Drive
February 2026
Upcoming
Stage 2A - Completion of Taylor Avenue roundabout and duplication of Haussman Drive
December 2027
Upcoming
Stage 2B - Further works
TBD
Upcoming
Stage 3
TBD

Haussman Drive has been identified as one of the key roads requiring upgrading works to support the full development in the Chisholm and Thornton North under the Section 94 Contributions Plan (now known as Section 7.11).

The traffic generation from the Thornton North development will result in a significant increase in traffic on the existing local and state road network, generating a need for new and/or upgraded traffic facilities, roads, bridges and intersections.

The project will be delivered in three stages. They are:

Glenroy Street upgrade from Railway Avenue to Government Road including both intersections:

  • Relocation of power poles and other utility services
  • Upgrade to a signalised intersection at Railway Avenue and Glenroy Street
  • Intersection improvements at Government Road and Glenroy Street/Haussman Drive
  • Reconstruction and widening of road pavement in both Glenroy Street and Railway Avenue
  • Drainage construction on Haussman Drive, Glenroy Street and Railway Avenue
  • Drainage and pavement improvements of North and South Laneways of Glenroy Street.​

Upgrade of Haussman Drive between Raymond Terrace Road and Taylor Avenue, including both intersections, will be completed in stages.

Stage 2A, set to commence in February 2026, will include:

  • Reconstruction and duplication of Haussman Drive to two lanes each direction (funded by Australian Government and Council)
  • Construction of a new roundabout at the Taylor Avenue intersection (funded by NSW Government and Council)
  • Utility adjustments and stormwater drainage construction
  • Shared pathway construction.
  •  

Stage 2B is subject to further grant funding and will include:

  • Reconstruction of Raymond Terrace Road and Haussman Drive intersection including traffic signals
  • Utility adjustments and stormwater drainage construction
  • Shared path construction connecting Harvest Boulevard, Chisholm and Settlers Boulevard, Chisholm with Haussman Drive.

Upgrade of Haussman Drive between Government Road and Taylor Avenue, connecting Stage 1 and 2, including:

  • Reconstruction and widening of Haussman Drive
  • Utility adjustments and stormwater drainage construction
  • Construction of a shared path along Haussman Drive.